Step-by-step guide to linking elements at different hierarchy levels in Plannerly. On screen, linking is called mapping, and the linking level is the Map leaf elements option.

Go to app.plannerly.com

1. Open the Model view

In your project, open Verify and switch to the Model view. The 3D model opens beside your task board. It must have finished processing before you can map to it.

2. Select the relevant model element

Click the required element inside the model. To move up to its parent, use the Select level higher button at the top right of the model.

3. Find the task

On the task board, find the card for the task you want to map these elements to.

Click the link icon on the task card. Its tooltip reads Map to Model Elements, and it opens a window of the same name.

5. Choose the linking level

Use the Map leaf elements checkbox:

  • Ticked (the default) - the lowest-level leaf elements of whatever you select are mapped to the task.
  • Unticked - the selected element itself is mapped, as an exact match. Use this when you want the task checked against that element, not each of its parts.

6. Expand hierarchy

Click Show Tree on the model toolbar, then expand the element hierarchy to review structure before confirming links.

7. Confirm and finalize linking

In the Map to Model Elements window, click Map selected to map the elements you selected, up to 50 at a time. For more than 50, select a level in the tree and click Map by rules. Plannerly then re-checks the task against the model.

This guide covered how to control linking levels for more precise and flexible model checking in Plannerly. To map many tasks at once, see How to map tasks to model elements with mapping rules.