Delete tasks and information requirements in Scope, one or many at once

Delete a single task from its window, clear many tasks at once with Delete Mode in Quick Assign, and delete information requirements from the project's Requirements list.

Contents

TL;DR - To delete one task, open it, select the three dots at the top of the task window and choose Delete Task. To delete many at once, open Quick Assign in Scope and switch on Delete Mode: then click a task, or hover a row, folder, group or milestone and choose Delete tasks. Plannerly lists exactly what will go before you confirm. To delete information requirements, open Requirements, select Manage, use the bin on each one (or Delete all) and Save. Deleting tasks can't be undone.


Who this is for

People whose project role can delete tasks - managers by default. A role can be allowed to delete all tasks, only assigned or unassigned ones, or none; see Change what each role can do. Deleting information requirements needs the Manage Information Requirements permission.

Why it matters

A scope is only useful if it matches what's really being delivered. Clearing out tasks that no longer apply keeps the delivery plan, the checks and every export honest.


Delete one task

  1. In Scope, click the task to open it.
  2. Select More options (the three dots) at the top of the task window.
  3. Choose Delete Task and confirm.

Delete many tasks at once with Delete Mode

  1. In Scope, select Quick Assign (the bolt) on the toolbar. The drawer opens on the right.
  2. At the bottom of the drawer, switch on Delete Mode. A card, Delete Mode - aim carefully, explains how it works.
Plannerly Scope with Quick Assign open and Delete Mode switched on at the bottom of the drawer, and the Delete Mode - aim carefully card
1: Quick Assign. 2: switch on Delete Mode. The card explains that the tasks inside go and the rows stay.
  1. Choose what to clear:
    • Click a task to delete that one task.
    • Hover a row and choose Delete tasks to delete every task in it while keeping the row, or Delete row to remove the row, its child rows and the tasks inside them.
    • Do the same on a folder, a group or a milestone to clear every task inside it.
A Scope row highlighted in red in Delete Mode with Delete row and Delete tasks buttons
Hover a row: 1 removes the row itself, 2 deletes only the tasks inside it.
  1. Check the confirmation. It names the row, folder, group or milestone, lists the tasks that will be permanently deleted, and says if information requirements attached to them go too. Then select Delete with the number of tasks.
Bulk delete confirmation in Plannerly Scope warning that the action cannot be undone, listing the tasks that will be permanently deleted, with a Delete 1 task button
Step 4: the confirmation lists every task that will go. The row itself stays.
  1. When you've finished, switch Delete Mode off or close the drawer.
Good to know: the first time you delete, Plannerly asks Continue deleting in this session? If you agree, single task cells delete as soon as you click them until you leave Delete Mode. Bigger deletes still show the summary first. If a Work Package is selected, you can choose to include tasks it hides, too.

Delete information requirements

  1. In Scope, select Requirements on the toolbar to open the project's requirements.
  2. Select Manage.
  3. Select the bin at the end of each requirement you want to remove, or Delete all at the top of the list. After Delete all, Undo delete brings them back, as long as you haven't saved.
  4. Select Save. Cancel leaves everything as it was.

Deleting a requirement here removes it from the project and from every task and element it was assigned to. To take requirements off some tasks but keep them in the project, unassign them instead - on a group row, use Unassign information requirements from this group. See Assign information requirements to tasks.

Why this matters: deleted tasks are gone for good, along with their history. If a task may come back, or you need a record of what was agreed, change its status or move it to a later milestone instead.

If it doesn't work

I don't see Delete Task or Delete Mode

Your role isn't allowed to delete these tasks. Ask a project manager, or ask them to change the role's Delete Tasks permission. Quick Assign also needs at least one row and one milestone in Scope.

It says the delete is too large

Very large deletes can't run in one go yet. Delete a smaller selection - one folder or milestone at a time.

A deleted task came back

If you saw Delete failed. Restored the task., the delete didn't go through - try again. Otherwise refresh the page. If the task is still there, tell us in Support with the project and task name.

I deleted the wrong tasks

Deleted tasks can't be restored. Recreate them, or import them again from a template or another project - see Importing Scope from a template or another project.


Common questions

How do I delete several tasks at once in Plannerly?

Open Quick Assign in Scope and switch on Delete Mode, then choose Delete tasks on a row, folder, group or milestone. Plannerly shows what will be deleted before you confirm.

Does deleting the tasks delete the row too?

No. Delete tasks keeps the row and clears its tasks. Use Delete row to remove the row as well.

Can I undo a delete?

No. Deleted tasks are permanent, which is why Plannerly lists them before you confirm.

How do I delete all information requirements in a project?

Open Requirements, select Manage, choose Delete all, then Save.

How do I delete a whole project instead?

Archive it, then delete it - see Archiving and deleting projects.