Skip to main content

How to import an IDS file into Plannerly

Import a buildingSMART IDS file into Scope so you can read, organise and check what it asks for, instead of reading XML.

Contents

TL;DR - In Scope, select Import, then Import IDS, drop in your .ids or .xml file (up to 5 MB) and select Import. Each specification becomes a scope row and its rules become requirements, all in one milestone.

Good to know - watch in your language: open the YouTube player settings (the gear icon), then under Subtitles/CC choose your language or use Auto-translate. If an auto-dubbed track is available, you can also switch the spoken voice under Audio track.

Who this is for

Project members with the Manage Scope Task Rows permission. Anyone else sees a message that bringing in an IDS is reserved for project managers.

Why it matters

An IDS (Information Delivery Specification) is buildingSMART's open file for stating what information a model must contain: which elements, which properties, which values. It is precise, but it is XML. Brought into Scope, it becomes something your team can read, organise, assign and check models against.

Import the IDS

  1. In Scope, select Import in the toolbar.
  2. Under the Scope section, select Import IDS ("Information Delivery Specification (buildingSMART)").
  3. Drop your file into Drag + Drop IDS File.
  4. Select Import. The drop alone does not start it.
Plannerly Import IDS window with an IDS file chosen and the Import button ready to create scope rows
Drop your IDS file in the box, then select Import.

See what came in

  1. Each IDS specification becomes a scope row. Its name is the row title and its description the subtitle.
  2. Expand a row to see its requirements, with their property sets, data types and allowed values.
  3. Select Requirements in the toolbar to review them all in one list.

An IDS imports into one milestone: the one named in the file's information section. If the project has no milestone with that name, Plannerly creates it. If the file names none, the rows go into "Untitled Milestone", which you can rename. To spread the requirements across other milestones, assign them to more tasks afterwards.

Plannerly Scope rows created from the IDS specifications, with External walls - fire and thermal expanded
Each IDS specification becomes a Scope row, with its requirements assigned beneath it.

Add checking rules the IDS is missing

  1. In the Requirements panel, select Manage.
  2. On a requirement with no rule, use the robot button to describe the rule in a sentence and select Generate, then Save.

Then use Verify to check a model against the requirements, as with any other requirement.

Plannerly Requirements panel in Manage mode listing the rules imported from the IDS file, with their groups
Open Requirements to see every rule the IDS file brought in, ready to edit.
Tip: Plannerly reads what it needs from the file rather than refusing it for small departures from the IDS schema, so files written by other tools usually come in.
Why this matters: a shared, structured specification beats a PDF that each team reads differently. Once it is in Scope, the same list drives assignments and checks.

If it doesn't work

Import IDS says it is reserved for project managers

You need the Manage Scope Task Rows permission. Ask a project manager to import it or to update your role.

Nothing happened after I dropped the file

Select Import in the window. The file must be .ids or .xml and no larger than 5 MB.

The rows landed in "Untitled Milestone"

The IDS did not name a milestone. Rename the milestone in the Scope grid, or add a milestone to the IDS and import again.

I opened the AI rule dialog and then cancelled, but the rule changed

Selecting the robot button switches the requirement's rule to Define Rule (Using AI) immediately, and Cancel does not undo it. Choose the original rule again from the Verification Rule dropdown.


Common questions

What is an IDS file?

An IDS (Information Delivery Specification) is a buildingSMART standard XML file that says what information a model must contain: which elements, which properties and which values.

How do I import an IDS file into Plannerly?

In Scope, select Import, then Import IDS, drop in the .ids or .xml file and select Import. Each specification becomes a scope row with its requirements.

Why did all my requirements land in one milestone?

An IDS carries one milestone in its information section, so everything imports there. Assign the requirements to other milestones in Scope afterwards.

Can I export an IDS again after editing?

Yes. Use Export, then IDS Specifications, to create a refined IDS in File Manager.



Take the free Certified Plannerly Professional course - every lesson is a short video like this one, with a certificate when you finish.