TL;DR - In Scope, select Import, then Import IDS, drop in your .ids or .xml file (up to 5 MB) and select Import. Each specification becomes a scope row and its rules become requirements, all in one milestone.
Who this is for
Project members with the Manage Scope Task Rows permission. Anyone else sees a message that bringing in an IDS is reserved for project managers.
Why it matters
An IDS (Information Delivery Specification) is buildingSMART's open file for stating what information a model must contain: which elements, which properties, which values. It is precise, but it is XML. Brought into Scope, it becomes something your team can read, organise, assign and check models against.
Import the IDS
- In Scope, select Import in the toolbar.
- Under the Scope section, select Import IDS ("Information Delivery Specification (buildingSMART)").
- Drop your file into Drag + Drop IDS File.
- Select Import. The drop alone does not start it.

See what came in
- Each IDS specification becomes a scope row. Its name is the row title and its description the subtitle.
- Expand a row to see its requirements, with their property sets, data types and allowed values.
- Select Requirements in the toolbar to review them all in one list.
An IDS imports into one milestone: the one named in the file's information section. If the project has no milestone with that name, Plannerly creates it. If the file names none, the rows go into "Untitled Milestone", which you can rename. To spread the requirements across other milestones, assign them to more tasks afterwards.

Add checking rules the IDS is missing
- In the Requirements panel, select Manage.
- On a requirement with no rule, use the robot button to describe the rule in a sentence and select Generate, then Save.
Then use Verify to check a model against the requirements, as with any other requirement.

If it doesn't work
Import IDS says it is reserved for project managers
You need the Manage Scope Task Rows permission. Ask a project manager to import it or to update your role.
Nothing happened after I dropped the file
Select Import in the window. The file must be .ids or .xml and no larger than 5 MB.
The rows landed in "Untitled Milestone"
The IDS did not name a milestone. Rename the milestone in the Scope grid, or add a milestone to the IDS and import again.
I opened the AI rule dialog and then cancelled, but the rule changed
Selecting the robot button switches the requirement's rule to Define Rule (Using AI) immediately, and Cancel does not undo it. Choose the original rule again from the Verification Rule dropdown.
Common questions
What is an IDS file?
An IDS (Information Delivery Specification) is a buildingSMART standard XML file that says what information a model must contain: which elements, which properties and which values.
How do I import an IDS file into Plannerly?
In Scope, select Import, then Import IDS, drop in the .ids or .xml file and select Import. Each specification becomes a scope row with its requirements.
Why did all my requirements land in one milestone?
An IDS carries one milestone in its information section, so everything imports there. Assign the requirements to other milestones in Scope afterwards.
Can I export an IDS again after editing?
Yes. Use Export, then IDS Specifications, to create a refined IDS in File Manager.
Related
- Hand out your requirements as an IDS file - the reverse.
- Tell every task team what to deliver, and when
- Import an IDS file into Plannerly (Help Center)
- buildingSMART: Information Delivery Specification (IDS) - the open standard itself.