Export a BIM model check report to PDF

Turn a Work Package's check results into a PDF with your cover page: information results for every task, plus Geometry check results for beta users, saved in File Manager.

Contents

TL;DR - Run your checks first. Then in Verify, select Export and choose Document. Select Add part, tick your Work Package under Verify and Cover Page under General, give the package a title and select Create. The PDF report lands in File Manager, ready to share or sign.


Who this is for

People with the Manage Files permission, which exporting needs. Managers have it by default. The report covers the Work Packages you choose, so the project needs at least one - see How to create a Work Package to check one set of tasks.

Why it matters

Results that stay on one screen help one person. A dated PDF with your cover shows the client, the design team or the people who approve payment exactly what was checked, against what, and what came back - without anyone needing a login.


Run the checks first

The report shows the latest results, so check before you export:

Create the report

  1. In Verify, select Export (the export icon in the toolbar), then Document. The document builder opens. Nothing is saved until you select Create.
  2. Select Add part. Under Verify, tick the Work Package you checked. Each Work Package is its own part.
  3. Under General, tick Cover Page to open the report with your project's cover.
  4. Check the preview, then set the Package title and who can open the file under Access.
  5. Select Create. Plannerly shows Preparing export... while it builds the PDF, then saves it in File Manager. You can keep working meanwhile.
From the Geometry check to the charts and the finished PDF report, with each task's information and geometry results. Watch this step in the replay.
Tip: exporting the same report every week? Save the setup as a preset, or let Plannerly create and email a new version on a schedule - see How to automate PDF exports.

What's in the report

For each Work Package, by milestone:

  • Model checks grouped by result: how many checks came back Missing, Incorrect and Correct, as a chart and as percentages.
  • Each task's information requirements: every requirement with its counts, so you can see which property failed on which task. Rules written with AI also say what they accept and what they're based on.
  • Geometry (beta users only): a summary of tasks checked, how many meet the pass mark and the average score, then each task's score, its Detail, Completeness, Placement and Purpose verdicts with their reasons, the pictures it judged and the summary.

The Geometry part appears when the person creating the report is in the beta testing community. To join, see Join the Plannerly beta testing community.

Share it or have it signed

Why this matters: under ISO 19650, information is checked against agreed requirements before it's shared and accepted. A report that shows the requirement, the result and the date is the record of that check - and the evidence when work is accepted and paid for.

If it doesn't work

"This feature is not available for your role"

Exporting needs the Manage Files permission. Ask a project manager to export the report, or to change your role.

Verify shows No Work Packages

The report is built per Work Package. Create one first, then come back to Add part.

There's no Geometry section

Either no Geometry check has finished on those tasks yet, or the person creating the report isn't in the beta testing community.

The preview says the project is too large

Very large projects can't show a live Verify preview. Select Create anyway: the finished PDF includes the complete Verify report.

Exports on the Free plan carry Plannerly branding. A paid plan or an active trial uses your own. See pricing.


Common questions

How do I export BIM model check results to PDF?

In Verify, select Export, then Document. Add your Work Package under Verify and a Cover Page under General, then select Create. The PDF is saved in File Manager.

Can I export the results to Excel instead?

Yes. Export, Scope Data creates an Excel file of tasks and requirements, and for a model version lists each task's mapped element IDs. Excel export isn't part of the Free plan.

Can I put several Work Packages in one report?

Yes. Tick each one under Verify in Add part. Each becomes its own part of the same PDF.

Does the report update when I check the model again?

A PDF is a snapshot. Create it again after the next check, or set up automatic versions so a fresh report is made on a schedule.



Take the free Certified Plannerly Professional course - short videos for every step, with a certificate when you finish.